An attic conversion is the cheapest square metre you'll ever add to a house, because the roof and the walls already exist. But it's also the job where corner-cutting is least visible and most consequential, because the parts that matter — the floor structure, the escape route and the fire separation — end up hidden.
The three things that decide whether it works
Headroom
You want around 2.4m of finished ceiling height over a usable proportion of the floor, and a minimum of 2m of clear headroom over the stairs. We measure this before anything else, because if the roof pitch doesn't give it, a dormer stops being optional.
Floor structure
The existing ceiling joists in most houses were sized to carry a plasterboard ceiling and nothing more. Converting to a habitable room means new floor joists, usually laid alongside or between the existing, sometimes carried on steel. This is not a place to economise.
Stairs
A proper fixed staircase, not a ladder, with compliant rise and going. Finding somewhere to land it without wrecking the room below is often the hardest design problem in the whole job.
Fire safety
Once an attic becomes a habitable room, the house has a third storey, and that changes the fire requirements for the whole building — not just the attic. Typically that means a protected escape route from the attic down to the front door, fire-rated doors onto that route, mains-wired interlinked smoke alarms across all floors, and an escape window in the attic room itself. We build to those requirements as standard.
Dormers
A dormer buys headroom and floor area, and it's what turns a cramped attic into a real room. We build flat-roof dormers with a warm-roof build-up — vapour control layer, PIR insulation, deck and a seamless GRP fibreglass finish — and clad the cheeks in horizontal timber, slate or render to suit the house.
A recent conversion in Dublin 5 took a 17.7m² attic to 25.9m² of usable floor area with a 4.67m wide rear dormer, two windows and 2.4m of ceiling height throughout.
Insulation
Insulation moves from the ceiling up to the rafter line, which changes how the roof behaves. Get the build-up wrong and you get condensation in the roof void. We insulate between and under the rafters with a continuous vapour control layer on the warm side, and maintain ventilation above where the build-up needs it.
What you get
- Structural floor upgrade, sized for habitable loading
- Dormer construction, or rooflights where the pitch allows
- Fixed staircase with compliant headroom
- Rafter-level insulation with a proper vapour control layer
- Fire doors, protected escape route and interlinked alarms
- Plastered, first and second fixed, ready to decorate
Common questions
Does a dormer need planning permission?
A dormer alters the profile of the roof, and in most cases that takes it outside the exempted development rules, meaning planning permission is required. Rooflights that sit flush with the roof plane are treated more leniently. Because the rules depend on the specific house, the elevation involved and what has been done to the property previously, always confirm your case with your local authority's planning section before proceeding.
Can I call the converted attic a bedroom?
Only if it meets the requirements for habitable space, which means adequate headroom, a compliant fixed staircase, a floor structure designed for habitable loading, and the fire safety measures that apply once a house has three storeys. A conversion that doesn't meet these is legally attic storage, and describing it as a bedroom can cause problems at sale, valuation or BER assessment.
How much headroom do I need?
As a working rule, around 2.4m of finished ceiling height over a meaningful proportion of the floor area, and at least 2m of clear headroom over the staircase. We measure the existing ridge height and rafter depth before quoting so you know early whether a dormer is needed.
How long does an attic conversion take?
A dormer conversion typically takes eight to fourteen weeks on site, depending on the size of the dormer, whether steel is needed for the floor, and window lead times.
Will the rest of the house be disrupted?
Some, unavoidably. The stairs have to land somewhere, alarms need wiring across all floors, and fire doors go in on the escape route. We sheet and protect the route in and out, and keep the mess contained as far as is practical.
Next step
Get a price on your job
Send us the address, what you're planning and any drawings you have. We'll come back with a realistic range before anyone spends time on a site visit.